Successfully migrated a manufacturing company's 20-year-old legacy systems to the cloud with zero production downtime and 40% cost reduction.
The Challenge
Industrial Solutions Corp operated on 20-year-old legacy systems that were becoming increasingly difficult and expensive to maintain, while limiting their ability to scale and innovate.
Our Approach
Executed a phased cloud migration strategy with parallel systems, gradual data migration, and comprehensive testing to ensure zero downtime.
Implementation Timeline
Total Duration: 32 weeks migration
Assessment & Planning
6 weeks
- Legacy system audit and dependency mapping
- Cloud architecture design
- Migration strategy development
- Risk assessment and mitigation planning
Infrastructure Setup
8 weeks
- Cloud infrastructure provisioning
- Network connectivity establishment
- Security controls implementation
- Monitoring and backup systems setup
Application Migration
14 weeks
- Application refactoring and containerization
- Database migration with synchronization
- Testing and validation in cloud environment
- Performance optimization and tuning
Cutover & Optimization
4 weeks
- Final data synchronization
- Production cutover execution
- Post-migration optimization
- Team training and knowledge transfer
Technical Architecture
Hybrid cloud architecture with containerized applications, managed databases, and automated scaling capabilities.
Results & Impact
Business Benefits
“The cloud migration was executed flawlessly with zero impact to our production operations. We now have a modern, scalable infrastructure that supports our growth plans while significantly reducing our IT costs.”